ASSESSING THE FACTORS CAUSING PROJECT COMPLETION DELAYS IN THE CONSTRUCTION SECTOR OF OMAN USING SEM-PLS
Corresponding Author(s) : Iman Suleiman Al Maktoumi
Humanities & Social Sciences Reviews,
Vol. 8 No. 3 (2020): May
Abstract
Purpose: The objectives of the study were to investigate the causes of the delays to analyze the factors causing the construction delay in Oman and to investigate the effects of such delays.
Design/methodology/approach: To carry out this study 210 samples were collected through a well-defined questionnaire from the construction stakeholders viz. the consultants, contractors, and the clients who were selected on a random sampling basis. Smart PLS for Structural Equation Modeling (SEM) technique was used to analyze the data to obtain the formative measurement models, the structured model, and the goodness of fit.
Findings: The results of the study reveal that the client-related factors, equipment-related factors, and material related factors have a significant impact on the completion delay in construction projects. The findings of the study also revealed that the Client related factors were – Delay in providing services, Delayed decision-making process, Allocation of insufficient time. Equipment related factors were – Existing low productive equipment, Unskillful Equipment operator, Breakdown of equipment and Outdated equipment; Material related factors were – Delay in supply of raw materials, Non-availability of materials, Change of materials during construction, Non-availability of accessories and Damaged materials.
Research limitations/Implications: The present study covers the stakeholders of the construction projects from selected regions only. The future studies can be extended to other projects and other regions as well.
Social implications: The study suggested that the clients’ cooperation especially in providing the contractors with the necessary equipment, facilities, and sufficient time will avoid such delays of the construction projects in Oman.
Originality/Value: Only very few have examined the completion delay of the construction projects in Oman using SEM-PLS and it is a first-hand study of its kind and the results will be useful to the stakeholders.
Keywords
Download Citation
Endnote/Zotero/Mendeley (RIS)BibTeX
- Acharya, N. K., Lee, Y., Kim, S. Y., Lee, J. C., & Kim, C. S. (2006). Analysis of construction delay factor: A Korean perspective. Paper presented at the Proceedings of the 7th Asia Pacific Industrial Engineering and Management Systems Conference.
- Al-Khalil, M. I., & Al-Ghafly, M. A. (1999). Delay in public utility projects in Saudi Arabia. International journal of project management, 17(2), 101-106. http://doi.org/10.1016/S0263-7863(98)00020-9 DOI: https://doi.org/10.1016/S0263-7863(98)00020-9
- Al-Momani, A. H. (2000). Construction delay: a quantitative analysis. International journal of project management, 18(1), 51-59. http://doi.org/10.1016/S0263-7863(98)00060-X DOI: https://doi.org/10.1016/S0263-7863(98)00060-X
- Al Harthi, A. (2005). Variation Orders in Construction Project in Oman: Problems & Remedies. Retrieved Feb.4, 2020, from Sultan Qaboos University https://www.squ.edu.om/Portals/22/project/CAE/CAE-2005-05-Eng.pdf
- Al Mohsin, M. A. C., & Alnuaimi, A. (2013). A Comparative Study on Causes of Delay Incompletion of Construction Projects in Oman. Journal of Construction Engineering, Technology & Management, 3(1), 1-6.
- Al Saadi, A. M. D., Latif, I., & Al-Nuaimi, A. S. (2018). Perspectives on Construction Time Overrun in Oman. Paper presented at the 1st National Conference on Civil and Architectural Engineering. https://www.researchgate.net/publication/324721493_PERSPECTIVES_ON_CONSTRUCTION_TIME_OVERRUN_IN_OMAN
- Ali, Y., Nusair, M. M., Alani, F., Khan, F. R., & Al Badi, L. (2017). Employment in the private sector in Oman: Sector-based approach for localization. Humanities & Social Sciences Reviews, ISSN, 5(1), 1-20. http://doi.org/10.18510/hssr.2017.511 DOI: https://doi.org/10.18510/hssr.2017.511
- Alnuaimi, A. S., & Mohsin, M. (2013). Causes of delay in completion of construction projects in Oman. Paper presented at the International Conference on Innovations in Engineering and Technology.
- Alnuaimi, A. S., Taha, R. A., Al Mohsin, M., & Al-Harthi, A. S. (2010). Causes, effects, benefits, and remedies of change orders on public construction projects in Oman. Journal of Construction Engineering and Management, 136(5), 615-622. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000154 DOI: https://doi.org/10.1061/(ASCE)CO.1943-7862.0000154
- Alsendi, M. (2015). Studying the effect of decision making on delayed construction projects. (Master of Engineering), Dissertation, The George Washington University, Manama, Kingdom of Bahrain.
- Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International journal of project management, 24(4), 349-357. http://doi.org/10.1016/j.ijproman.2005.11.010 DOI: https://doi.org/10.1016/j.ijproman.2005.11.010
- Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995). Causes of delay in large building construction projects. Journal of management in engineering, 11(2), 45-50. http://doi.org/10.1061/(ASCE)0742-597X(1995)11:2(45) DOI: https://doi.org/10.1061/(ASCE)0742-597X(1995)11:2(45)
- Bagozzi, R. P., & Yi, Y. (1988). On the evaluation of structural equation models. Journal of the academy of marketing science, 16(1), 74-94. https://doi.org/10.1007/BF02723327 DOI: https://doi.org/10.1007/BF02723327
- Bhatia, N. (2017). Oman-listed contractor Galfar hit by payment delays in 2017. Construction Week Online.
- Chan, D. W., & Kumaraswamy, M. M. (1997). A comparative study of causes of time overruns in Hong Kong construction projects. International journal of project management, 15(1), 55-63. http://doi.org/10.1016/S0263-7863(96)00039-7 DOI: https://doi.org/10.1016/S0263-7863(96)00039-7
- Cohen, P., West, S. G., & Aiken, L. S. (2014). Applied multiple regression/correlation analysis for the behavioral sciences: Psychology Press. DOI: https://doi.org/10.4324/9781410606266
- Comrey, A. L., & Lee, H. B. (2013). A first course in factor analysis: Psychology press. DOI: https://doi.org/10.4324/9781315827506
- Divakar, K., & Subramanian, K. (2009). Critical success factors in the real-time monitoring of construction projects. Research Journal of Applied Sciences, Engineering and Technology, 1(2), 35-39.
- Emam, H., Farrell, P., & Abdelaal, M. (2015). Causes of delay on infrastructure projects in Qatar. Paper presented at the Proceedings of the 31st Annual ARCOM Conference, Lincoln, UK, Association of Researchers in Construction Management, Nottingham, UK.
- Faridi, A. S., & Elâ€Sayegh, S. M. (2006). Significant factors causing delay in the UAE construction industry. Construction Management and Economics, 24(11), 1167-1176. http://doi.org/10.1080/01446190600827033 DOI: https://doi.org/10.1080/01446190600827033
- Fornell, C., & Larcker, D. F. (1981). Evaluating structural equation models with unobservable variables and measurement error. Journal of marketing research, 18(1), 39-50. https://doi.org/10.1177/002224378101800104 DOI: https://doi.org/10.1177/002224378101800104
- Gefen, D., Straub, D., & Boudreau, M.-C. (2000). Structural equation modeling and regression: Guidelines for research practice. Communications of the association for information systems, 4(1), 1-78. https://doi.org/10.17705/1CAIS.00407 DOI: https://doi.org/10.17705/1CAIS.00407
- Gündüz, M., Nielsen, Y., & Özdemir, M. (2013). Quantification of delay factors using the relative importance index method for construction projects in Turkey. Journal of management in engineering, 29(2), 133-139. http://doi.org/10.1061/(ASCE)ME.1943-5479.0000129 DOI: https://doi.org/10.1061/(ASCE)ME.1943-5479.0000129
- Hair, J. F., Black, W. C., Babin, B. J., Anderson, R. E., & Tatham, R. L. (1998). Multivariate data analysis (Vol. 5, No. 3, pp. 207-219): Upper Saddle River, NJ: Prentice-Hall.
- Hair, J. F., Sarstedt, M., Ringle, C. M., & Mena, J. A. (2012). An assessment of the use of partial least squares structural equation modeling in marketing research. Journal of the academy of marketing science, 40(3), 414-433. https://doi.org/10.1007/s11747-011-0261-6 DOI: https://doi.org/10.1007/s11747-011-0261-6
- Hari, P., & Pandey, M. (2016). Causes of the Time Delay in Construction Housing Projects in Gwalior Division. International Research Journal of Engineering and Technology, 3(12), 337-341.
- Henderson, D., Sheetz, S. D., & Trinkle, B. S. (2012). The determinants of inter-organizational and internal in-house adoption of XBRL: A structural equation model. International journal of accounting information systems, 13(2), 109-140. https://doi.org/10.1016/j.accinf.2012.02.001 DOI: https://doi.org/10.1016/j.accinf.2012.02.001
- Huang, C.-C., Wang, Y.-M., Wu, T.-W., & Wang, P.-A. (2013). An empirical analysis of the antecedents and performance consequences of using the Moodle platform. International Journal of Information and Education Technology, 3(2), 217. http://doi.org/10.7763/IJIET.2013.V3.267 DOI: https://doi.org/10.7763/IJIET.2013.V3.267
- Hulland, J. (1999). Use of partial least squares (PLS) in strategic management research: A review of four recent studies. Strategic management journal, 20(2), 195-204. https://doi.org/10.1002/(SICI)1097-0266(199902)20:2<195::AID-SMJ13>3.0.CO;2-7 DOI: https://doi.org/10.1002/(SICI)1097-0266(199902)20:2<195::AID-SMJ13>3.0.CO;2-7
- Iyer, K., & Jha, K. (2005). Factors affecting cost performance: evidence from Indian construction projects. International journal of project management, 23(4), 283-295. doi: http://doi.org/10.1016/j.ijproman.2004.10.003 DOI: https://doi.org/10.1016/j.ijproman.2004.10.003
- Kadir, M. A., Lee, W., Jaafar, M., Sapuan, S., & Ali, A. (2005). Factors affecting construction labour productivity for Malaysian residential projects. Structural survey, 23(1), 42-54. http://doi.org/10.1108/02630800510586907 DOI: https://doi.org/10.1108/02630800510586907
- Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management & Economics, 15(1), 83-94. http://doi.org/10.1080/014461997373132 DOI: https://doi.org/10.1080/014461997373132
- Kraiem, Z. M., & Diekmann, J. E. (1987). Concurrent delays in construction projects. Journal of Construction Engineering and Management, 113(4), 591-602. http://doi.org/10.1061/(ASCE)0733-9364(1987)113:4(591) DOI: https://doi.org/10.1061/(ASCE)0733-9364(1987)113:4(591)
- Latif, I., Al Saadi, A. M. D., & Rahman, I. A. (2019). Identification of Delay Factor in Oman Construction Industry. International Journal of Sustainable Construction Engineering and Technology, 10(1), 34-45. https://doi.org/10.30880/ijscet.2019.10.01.004 DOI: https://doi.org/10.30880/ijscet.2019.10.01.004
- Le-Hoai, L., Dai Lee, Y., & Lee, J. Y. (2008). Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of civil engineering, 12(6), 367-377. http://doi.org/10.1007/s12205-008-0367-7 DOI: https://doi.org/10.1007/s12205-008-0367-7
- Ling, F. Y. Y., & Hoi, L. (2006). Risks faced by Singapore firms when undertaking construction projects in India. International journal of project management, 24(3), 261-270. http://doi.org/10.1016/j.ijproman.2005.11.003 DOI: https://doi.org/10.1016/j.ijproman.2005.11.003
- Malik, M. J., & Mitchell, H. (2018). Construction and projects in Oman: Overview. from Al-Busaidy Mansoor Jamal & Co. https://www.amjoman.com/wp-content/uploads/2019/01/Construction-and-projects-in-Oman-overview.pdf
- Nkado, R. N. (1995). Construction time-influencing factors: the contractor's perspective. Construction Management and Economics, 13(1), 81-89. http://doi.org/10.1080/01446199500000009 DOI: https://doi.org/10.1080/01446199500000009
- Odeh, A. M., & Battaineh, H. T. (2002). Causes of construction delay: traditional contracts. International journal of project management, 20(1), 67-73. DOI: https://doi.org/10.1016/S0263-7863(00)00037-5
- Odeyinka, H. A., & Yusif, A. (1997). The causes and effects of construction delays on completion cost of housing projects in Nigeria. Journal of Financial Management of Property and Construction, 2, 31-44.
- Ogweno, B., Muturi, W., & Rambo, C. (2016). Determinants of timely completion of road Construction projects financed by Kenya Roads board in Kisumu County. International Journal of Economics, Commerce and Management, 4(11), 361-364.
- Olawale, Y. A., & Sun, M. (2010). Cost and time control of construction projects: inhibiting factors and mitigating measures in practice. Construction Management and Economics, 28(5), 509-526. http://doi.org/10.1080/01446191003674519 DOI: https://doi.org/10.1080/01446191003674519
- Pourrostam, T., Ismail, A., & Mansournejad, M. (2011). Identification of Success Factors in Minimizing Delays on Construction Projects in IAU-Shoushtar Branch-Iran. Paper presented at the Applied Mechanics and Materials. DOI: https://doi.org/10.4028/www.scientific.net/AMM.94-96.2189
- Ren, Z., Atout, M., & Jones, J. (2008). Root causes of construction project delays in Dubai. Paper presented at the Procs 24th Annual ARCOM Conference.
- Sacks, R., & Goldin, M. (2007). Lean management model for construction of high-rise apartment buildings. Journal of Construction Engineering and Management, 133(5), 374-384. http://doi.org/10.1061/(ASCE)0733-9364(2007)133:5(374) DOI: https://doi.org/10.1061/(ASCE)0733-9364(2007)133:5(374)
- Saeed, S. A. A. (2009). Delay to Projects-cause, effect and measures to reduce/eliminate delay by mitigation/acceleration. (Project Management Programme Doctoral Dissertation), British University in Dubai. Retrieved from https://bspace.buid.ac.ae/bitstream/1234/234/1/60046.pdf
- Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International journal of project management, 25(5), 517-526. http://doi.org/10.1016/j.ijproman.2006.11.007 DOI: https://doi.org/10.1016/j.ijproman.2006.11.007
- Shaibany, S. (2015, Dec.12, 2015). Further delay in completion of airports would affect Oman's economy, Opinion Columnist, Times of Oman.
- Sweis, G., Sweis, R., Hammad, A. A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International journal of project management, 26(6), 665-674. http://doi.org/10.1016/j.ijproman.2007.09.009 DOI: https://doi.org/10.1016/j.ijproman.2007.09.009
- Tenenhaus, M., Vinzi, V. E., Chatelin, Y.-M., & Lauro, C. (2005). PLS path modeling. Computational statistics & data analysis, 48(1), 159-205. https://doi.org/10.1016/j.csda.2004.03.005 DOI: https://doi.org/10.1016/j.csda.2004.03.005
- Toor, S. U. R., & Ogunlana, S. O. (2008). Problems causing delays in major construction projects in Thailand. Construction Management and Economics, 26(4), 395-408. http://doi.org/10.1080/01446190801905406 DOI: https://doi.org/10.1080/01446190801905406
- Umar, T. (2018). Causes of delay in construction projects in Oman. Middle East Journal of Management, 5(2), 121-136. http://doi.org/10.1504/MEJM.2018.091132 DOI: https://doi.org/10.1504/MEJM.2018.10012114
- Yusuwan, N. M., & Adnan, H. (2013). Issues associated with extension of time (EoT) claim in Malaysian construction industry. Procedia Technology, 9, 740-749. http://doi.org/10.1016/j.protcy.2013.12.082 DOI: https://doi.org/10.1016/j.protcy.2013.12.082
References
Acharya, N. K., Lee, Y., Kim, S. Y., Lee, J. C., & Kim, C. S. (2006). Analysis of construction delay factor: A Korean perspective. Paper presented at the Proceedings of the 7th Asia Pacific Industrial Engineering and Management Systems Conference.
Al-Khalil, M. I., & Al-Ghafly, M. A. (1999). Delay in public utility projects in Saudi Arabia. International journal of project management, 17(2), 101-106. http://doi.org/10.1016/S0263-7863(98)00020-9 DOI: https://doi.org/10.1016/S0263-7863(98)00020-9
Al-Momani, A. H. (2000). Construction delay: a quantitative analysis. International journal of project management, 18(1), 51-59. http://doi.org/10.1016/S0263-7863(98)00060-X DOI: https://doi.org/10.1016/S0263-7863(98)00060-X
Al Harthi, A. (2005). Variation Orders in Construction Project in Oman: Problems & Remedies. Retrieved Feb.4, 2020, from Sultan Qaboos University https://www.squ.edu.om/Portals/22/project/CAE/CAE-2005-05-Eng.pdf
Al Mohsin, M. A. C., & Alnuaimi, A. (2013). A Comparative Study on Causes of Delay Incompletion of Construction Projects in Oman. Journal of Construction Engineering, Technology & Management, 3(1), 1-6.
Al Saadi, A. M. D., Latif, I., & Al-Nuaimi, A. S. (2018). Perspectives on Construction Time Overrun in Oman. Paper presented at the 1st National Conference on Civil and Architectural Engineering. https://www.researchgate.net/publication/324721493_PERSPECTIVES_ON_CONSTRUCTION_TIME_OVERRUN_IN_OMAN
Ali, Y., Nusair, M. M., Alani, F., Khan, F. R., & Al Badi, L. (2017). Employment in the private sector in Oman: Sector-based approach for localization. Humanities & Social Sciences Reviews, ISSN, 5(1), 1-20. http://doi.org/10.18510/hssr.2017.511 DOI: https://doi.org/10.18510/hssr.2017.511
Alnuaimi, A. S., & Mohsin, M. (2013). Causes of delay in completion of construction projects in Oman. Paper presented at the International Conference on Innovations in Engineering and Technology.
Alnuaimi, A. S., Taha, R. A., Al Mohsin, M., & Al-Harthi, A. S. (2010). Causes, effects, benefits, and remedies of change orders on public construction projects in Oman. Journal of Construction Engineering and Management, 136(5), 615-622. https://doi.org/10.1061/(ASCE)CO.1943-7862.0000154 DOI: https://doi.org/10.1061/(ASCE)CO.1943-7862.0000154
Alsendi, M. (2015). Studying the effect of decision making on delayed construction projects. (Master of Engineering), Dissertation, The George Washington University, Manama, Kingdom of Bahrain.
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International journal of project management, 24(4), 349-357. http://doi.org/10.1016/j.ijproman.2005.11.010 DOI: https://doi.org/10.1016/j.ijproman.2005.11.010
Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995). Causes of delay in large building construction projects. Journal of management in engineering, 11(2), 45-50. http://doi.org/10.1061/(ASCE)0742-597X(1995)11:2(45) DOI: https://doi.org/10.1061/(ASCE)0742-597X(1995)11:2(45)
Bagozzi, R. P., & Yi, Y. (1988). On the evaluation of structural equation models. Journal of the academy of marketing science, 16(1), 74-94. https://doi.org/10.1007/BF02723327 DOI: https://doi.org/10.1007/BF02723327
Bhatia, N. (2017). Oman-listed contractor Galfar hit by payment delays in 2017. Construction Week Online.
Chan, D. W., & Kumaraswamy, M. M. (1997). A comparative study of causes of time overruns in Hong Kong construction projects. International journal of project management, 15(1), 55-63. http://doi.org/10.1016/S0263-7863(96)00039-7 DOI: https://doi.org/10.1016/S0263-7863(96)00039-7
Cohen, P., West, S. G., & Aiken, L. S. (2014). Applied multiple regression/correlation analysis for the behavioral sciences: Psychology Press. DOI: https://doi.org/10.4324/9781410606266
Comrey, A. L., & Lee, H. B. (2013). A first course in factor analysis: Psychology press. DOI: https://doi.org/10.4324/9781315827506
Divakar, K., & Subramanian, K. (2009). Critical success factors in the real-time monitoring of construction projects. Research Journal of Applied Sciences, Engineering and Technology, 1(2), 35-39.
Emam, H., Farrell, P., & Abdelaal, M. (2015). Causes of delay on infrastructure projects in Qatar. Paper presented at the Proceedings of the 31st Annual ARCOM Conference, Lincoln, UK, Association of Researchers in Construction Management, Nottingham, UK.
Faridi, A. S., & Elâ€Sayegh, S. M. (2006). Significant factors causing delay in the UAE construction industry. Construction Management and Economics, 24(11), 1167-1176. http://doi.org/10.1080/01446190600827033 DOI: https://doi.org/10.1080/01446190600827033
Fornell, C., & Larcker, D. F. (1981). Evaluating structural equation models with unobservable variables and measurement error. Journal of marketing research, 18(1), 39-50. https://doi.org/10.1177/002224378101800104 DOI: https://doi.org/10.1177/002224378101800104
Gefen, D., Straub, D., & Boudreau, M.-C. (2000). Structural equation modeling and regression: Guidelines for research practice. Communications of the association for information systems, 4(1), 1-78. https://doi.org/10.17705/1CAIS.00407 DOI: https://doi.org/10.17705/1CAIS.00407
Gündüz, M., Nielsen, Y., & Özdemir, M. (2013). Quantification of delay factors using the relative importance index method for construction projects in Turkey. Journal of management in engineering, 29(2), 133-139. http://doi.org/10.1061/(ASCE)ME.1943-5479.0000129 DOI: https://doi.org/10.1061/(ASCE)ME.1943-5479.0000129
Hair, J. F., Black, W. C., Babin, B. J., Anderson, R. E., & Tatham, R. L. (1998). Multivariate data analysis (Vol. 5, No. 3, pp. 207-219): Upper Saddle River, NJ: Prentice-Hall.
Hair, J. F., Sarstedt, M., Ringle, C. M., & Mena, J. A. (2012). An assessment of the use of partial least squares structural equation modeling in marketing research. Journal of the academy of marketing science, 40(3), 414-433. https://doi.org/10.1007/s11747-011-0261-6 DOI: https://doi.org/10.1007/s11747-011-0261-6
Hari, P., & Pandey, M. (2016). Causes of the Time Delay in Construction Housing Projects in Gwalior Division. International Research Journal of Engineering and Technology, 3(12), 337-341.
Henderson, D., Sheetz, S. D., & Trinkle, B. S. (2012). The determinants of inter-organizational and internal in-house adoption of XBRL: A structural equation model. International journal of accounting information systems, 13(2), 109-140. https://doi.org/10.1016/j.accinf.2012.02.001 DOI: https://doi.org/10.1016/j.accinf.2012.02.001
Huang, C.-C., Wang, Y.-M., Wu, T.-W., & Wang, P.-A. (2013). An empirical analysis of the antecedents and performance consequences of using the Moodle platform. International Journal of Information and Education Technology, 3(2), 217. http://doi.org/10.7763/IJIET.2013.V3.267 DOI: https://doi.org/10.7763/IJIET.2013.V3.267
Hulland, J. (1999). Use of partial least squares (PLS) in strategic management research: A review of four recent studies. Strategic management journal, 20(2), 195-204. https://doi.org/10.1002/(SICI)1097-0266(199902)20:2<195::AID-SMJ13>3.0.CO;2-7 DOI: https://doi.org/10.1002/(SICI)1097-0266(199902)20:2<195::AID-SMJ13>3.0.CO;2-7
Iyer, K., & Jha, K. (2005). Factors affecting cost performance: evidence from Indian construction projects. International journal of project management, 23(4), 283-295. doi: http://doi.org/10.1016/j.ijproman.2004.10.003 DOI: https://doi.org/10.1016/j.ijproman.2004.10.003
Kadir, M. A., Lee, W., Jaafar, M., Sapuan, S., & Ali, A. (2005). Factors affecting construction labour productivity for Malaysian residential projects. Structural survey, 23(1), 42-54. http://doi.org/10.1108/02630800510586907 DOI: https://doi.org/10.1108/02630800510586907
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management & Economics, 15(1), 83-94. http://doi.org/10.1080/014461997373132 DOI: https://doi.org/10.1080/014461997373132
Kraiem, Z. M., & Diekmann, J. E. (1987). Concurrent delays in construction projects. Journal of Construction Engineering and Management, 113(4), 591-602. http://doi.org/10.1061/(ASCE)0733-9364(1987)113:4(591) DOI: https://doi.org/10.1061/(ASCE)0733-9364(1987)113:4(591)
Latif, I., Al Saadi, A. M. D., & Rahman, I. A. (2019). Identification of Delay Factor in Oman Construction Industry. International Journal of Sustainable Construction Engineering and Technology, 10(1), 34-45. https://doi.org/10.30880/ijscet.2019.10.01.004 DOI: https://doi.org/10.30880/ijscet.2019.10.01.004
Le-Hoai, L., Dai Lee, Y., & Lee, J. Y. (2008). Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE Journal of civil engineering, 12(6), 367-377. http://doi.org/10.1007/s12205-008-0367-7 DOI: https://doi.org/10.1007/s12205-008-0367-7
Ling, F. Y. Y., & Hoi, L. (2006). Risks faced by Singapore firms when undertaking construction projects in India. International journal of project management, 24(3), 261-270. http://doi.org/10.1016/j.ijproman.2005.11.003 DOI: https://doi.org/10.1016/j.ijproman.2005.11.003
Malik, M. J., & Mitchell, H. (2018). Construction and projects in Oman: Overview. from Al-Busaidy Mansoor Jamal & Co. https://www.amjoman.com/wp-content/uploads/2019/01/Construction-and-projects-in-Oman-overview.pdf
Nkado, R. N. (1995). Construction time-influencing factors: the contractor's perspective. Construction Management and Economics, 13(1), 81-89. http://doi.org/10.1080/01446199500000009 DOI: https://doi.org/10.1080/01446199500000009
Odeh, A. M., & Battaineh, H. T. (2002). Causes of construction delay: traditional contracts. International journal of project management, 20(1), 67-73. DOI: https://doi.org/10.1016/S0263-7863(00)00037-5
Odeyinka, H. A., & Yusif, A. (1997). The causes and effects of construction delays on completion cost of housing projects in Nigeria. Journal of Financial Management of Property and Construction, 2, 31-44.
Ogweno, B., Muturi, W., & Rambo, C. (2016). Determinants of timely completion of road Construction projects financed by Kenya Roads board in Kisumu County. International Journal of Economics, Commerce and Management, 4(11), 361-364.
Olawale, Y. A., & Sun, M. (2010). Cost and time control of construction projects: inhibiting factors and mitigating measures in practice. Construction Management and Economics, 28(5), 509-526. http://doi.org/10.1080/01446191003674519 DOI: https://doi.org/10.1080/01446191003674519
Pourrostam, T., Ismail, A., & Mansournejad, M. (2011). Identification of Success Factors in Minimizing Delays on Construction Projects in IAU-Shoushtar Branch-Iran. Paper presented at the Applied Mechanics and Materials. DOI: https://doi.org/10.4028/www.scientific.net/AMM.94-96.2189
Ren, Z., Atout, M., & Jones, J. (2008). Root causes of construction project delays in Dubai. Paper presented at the Procs 24th Annual ARCOM Conference.
Sacks, R., & Goldin, M. (2007). Lean management model for construction of high-rise apartment buildings. Journal of Construction Engineering and Management, 133(5), 374-384. http://doi.org/10.1061/(ASCE)0733-9364(2007)133:5(374) DOI: https://doi.org/10.1061/(ASCE)0733-9364(2007)133:5(374)
Saeed, S. A. A. (2009). Delay to Projects-cause, effect and measures to reduce/eliminate delay by mitigation/acceleration. (Project Management Programme Doctoral Dissertation), British University in Dubai. Retrieved from https://bspace.buid.ac.ae/bitstream/1234/234/1/60046.pdf
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International journal of project management, 25(5), 517-526. http://doi.org/10.1016/j.ijproman.2006.11.007 DOI: https://doi.org/10.1016/j.ijproman.2006.11.007
Shaibany, S. (2015, Dec.12, 2015). Further delay in completion of airports would affect Oman's economy, Opinion Columnist, Times of Oman.
Sweis, G., Sweis, R., Hammad, A. A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International journal of project management, 26(6), 665-674. http://doi.org/10.1016/j.ijproman.2007.09.009 DOI: https://doi.org/10.1016/j.ijproman.2007.09.009
Tenenhaus, M., Vinzi, V. E., Chatelin, Y.-M., & Lauro, C. (2005). PLS path modeling. Computational statistics & data analysis, 48(1), 159-205. https://doi.org/10.1016/j.csda.2004.03.005 DOI: https://doi.org/10.1016/j.csda.2004.03.005
Toor, S. U. R., & Ogunlana, S. O. (2008). Problems causing delays in major construction projects in Thailand. Construction Management and Economics, 26(4), 395-408. http://doi.org/10.1080/01446190801905406 DOI: https://doi.org/10.1080/01446190801905406
Umar, T. (2018). Causes of delay in construction projects in Oman. Middle East Journal of Management, 5(2), 121-136. http://doi.org/10.1504/MEJM.2018.091132 DOI: https://doi.org/10.1504/MEJM.2018.10012114
Yusuwan, N. M., & Adnan, H. (2013). Issues associated with extension of time (EoT) claim in Malaysian construction industry. Procedia Technology, 9, 740-749. http://doi.org/10.1016/j.protcy.2013.12.082 DOI: https://doi.org/10.1016/j.protcy.2013.12.082